St Georges Court

Pre-commencement works​

  • Fire Engineers and London Fire Brigade carry out independent reviews of building and fire safety design proposals
    Estimated to start February 2021 ​and finish April 2021
  • Building Control reviews and approves design works
    Estimated to start April 2021 ​and finish August 2021
  • Carry out consultation process for major works with leaseholders
    Started March 2022 ​and finished April 2022

Construction works 

  • Erect scaffold
    Estimated to start November 2022 and finish January 2023
  • Install new fire rated cavity barriers around penetrations through the external walls
    Estimated to start February 2023 and finish April 2023
  • Replace balcony soffits with modern compliant materials
    Estimated to start February 2023 and finish July 2023
  • Undertake fire upgrade works to wall between external riser shafts and flats
    Estimated to start April 2023 and finish July 2023
  • Carry out works to communal walkways and windows
    Estimated to start April 2023 and finish July 2023
  • Remove and renew cavity wall insulation
    Estimated to start February 2023 and finish April 2023
  • Carry out mechanical and electrical related works e.g. installation of fire alarms (subject to Fire Engineer’s report)
    Estimated to start April 2023 and finish September 2023
  • Remove scaffolding
    Estimated to start July 2023 and finish August 2023