Northwood Tower
Pre commencement works
- Fire engineers and London fire brigade carry out independent reviews of building and fire safety design proposals.
Estimated to start January 2021 and finish February 2021 - Carry out consultation process for major works with leaseholders
Started March 2022 and finished April 2022 - Building Control reviews and approves design
Estimated to start March 2021 and finish July 2021
Construction works
- Erect scaffold
Estimated to start August 2022 and finish October 2022 - Replace balcony soffits with modern compliant materials
Estimated to start November 2022 and finish February 2023 - Install new infill panels to external windows to bin chute
Estimated to start December 2022 and finish February 2023 - Remove scaffolding
Estimated to start November 2022 and finish December 2022 - Carry out mechanical and electrical related works e.g. installation of fire alarms (subject to fire engineer’s report)
Estimated to start April 2023 and finish September 2023