Last updated: 7 November 2023
Next review: 7 November 2024
Burrell and Rayner towers
Pre-commencement works
- Fire Engineers and London Fire Brigade carry out independent reviews of building and fire safety design proposals.
- Design works are estimated to be complete in August 2023
- Building Control reviews and approves the design.
- Estimated to start in late September 2023
- Submitted Planning Application for approval in July 2023
- Carry out consultation process for major works with leaseholders in August/September 2023
Construction Works
- Erect scaffolding – estimated to start October 2023
- Carry out mechanical and electrical-related work. For example, the installation of fire alarms, sprinklers and associated infrastructure.
- Install new fire-rated cavity barriers around penetrations through the external walls
- Replace windows with modern compliant materials
- Replace curtain walling system to stairwell with new compliant materials
Estimated to start September 2023 and finish January 2025