What are CIL surcharges?

Surcharges apply if you pay late or miss required CIL notices, and interest is added until paid.

Under the regulations, failure to follow the correct CIL procedure can lead to surcharges being added.

  • For late payment – 5% of the chargeable amount or £200 (whichever is greater) may be charged after 30 days. This charge will be added again after 6 months, and after 12 months on any outstanding amount.
  • If the development has started or been completed and we haven't received a Commencement Notice. 20% of the chargeable amount payable, or £2,500 (whichever is the lower amount).
  • Late payment interest is paid starting on the day payment was due at 2.5 percentage points above the Bank of England base rate.
  • Failure to comply with an information notice within 14 days – 20% of the chargeable amount up to a maximum of £1,000.
  • For failure to notify us of a disqualifying event within 14 days - 20% of the chargeable amount up to a maximum of £2,500.
  • For failure to submit a Notice of Chargeable Development – 20% of the chargeable amount up to a maximum of £2,500.
  • Where we have to apportion liability between different owners - £500 on each owner.