The Building Safety Levy is a new national levy introduced by the Government under the Building Safety Act 2022. It will apply to certain new residential developments in England from 1 October 2026.
The levy is designed to help fund the remediation of unsafe building cladding and improve building safety across the country. Developers of qualifying residential schemes will be required to pay the levy as part of the building control process.
As the local authority with building control responsibilities, we are required to collect the levy and transfer the funds to the Ministry of Housing, Communities and Local Government (MHCLG).
Who is required to pay the levy
The levy applies to most new residential developments in England that meet the criteria set out in the Building Safety Levy Regulations. The Building Safety Levy applies to:
- new residential housing developments
- purpose-built student accommodation (PBSA)
- residential developments that meet the government's definition of a chargeable development
The levy is payable by the developer or client responsible for the development.
Developments that are exempt
Certain developments are exempt from the levy, including:
- residential developments with fewer than 10 homes
- affordable housing
- supported housing
- housing provided by registered non-profit housing providers and their wholly owned subsidiaries
- other development types exempt under the Regulations
Developers may be required to provide evidence to support any exemption claim.
How we calculate the levy
The levy is charged on a £ per square metre basis using the amount of chargeable residential floorspace created by the development. Levy rates are set by the Government and vary between local authority areas,
Developments built on qualifying previously developed land (brownfield land) may be eligible for a 50% discounted levy rate, subject to meeting the criteria set out in the Regulations.
The applicable rates for each local authority area can be found in the Government's Building Safety Levy guidance.
Information required from developers
From 1 October 2026, developers will need to provide Building Safety Levy information alongside relevant building control applications and notices. Additional information will also be required before commencement to enable the levy charge to be calculated.
Applications that do not include the required levy information may be rejected.
Developers should refer to the Government's levy guidance and information forms when preparing submissions.
When levy payments are due
Once the levy has been assessed, a Levy Determination Notice will be issued confirming the amount payable.
The levy must be paid before the earlier of:
- occupation of the development; or
- completion of the development for building control purposes.
Failure to pay the levy may result in the withholding of the completion certificate or final certificate.
Reviews, refunds and appeals
If a developer disagrees with:
- a levy determination
- a refund decision
- any other levy decision made by the collecting authority
they may request a review by the local authority within the timescales specified in the Regulations.
Following a review, appeals may be made to the First-tier Tribunal where permitted by the Regulations.
Further guidance
The Building Safety Levy is governed by national legislation and guidance issued by the Government.
Useful resources:
- Building Safety Levy: Government Guidance
- Building Safety Levy (England) Regulations 2025
- Building Safety Levy Rates and Calculations
- Building Safety Levy Proformas and Information Annexes for Developers
For the latest guidance, visit GOV.UK.
Find guidance on building regulations, choose the correct application type, and submit your application on the Make a building regulation application page.
Building Control team
If you have questions about how the Building Safety Levy applies to your development, contact the building control team.
Further information
When the Building Safety Levy applies
The levy applies to qualifying residential developments in England from 1 October 2026 and is linked to the building control approval process. It generally applies to new residential floorspace created through major residential development, unless an exemption applies.
Small development exemption
The levy does not apply to developments creating fewer than 10 homes.
Developers may still need to provide information to demonstrate that the development qualifies for the exemption.
Affordable and supported housing exemptions
The levy does not apply to:
- affordable housing
- supported housing
- housing delivered by registered non-profit providers of social housing and their wholly owned subsidiaries
You will normally need to provide evidence to support an exemption claim.
Information required with a building control application
You must provide Building Safety Levy information when submitting relevant building control applications or notices.
Additional information and supporting evidence will be required before work starts so the levy can be assessed accurately.
Applications may be rejected if the required information is not provided.
Levy determination notices
Once the Council has assessed the information submitted, it will issue a Levy Determination Notice confirming:
- the amount payable
- how the levy has been calculated
- any exemptions or discounts applied
- payment arrangements and deadlines
Levy payment deadlines
The levy must be paid before the earlier of:
- occupation of the development
- building control completion
Failure to pay may result in completion certification being withheld.
Reviews and appeals
If you disagree with a levy determination, refund decision or another levy-related decision, you can request a review by the Council.
If you remain dissatisfied following the review, you may be able to appeal to the First-tier Tribunal.
Changes to a development after levy assessment
The Building Safety Levy Regulations include provisions for project changes, recalculations and refunds where appropriate.
You should notify the Council as soon as possible if there are material changes affecting:
- floorspace
- the number of homes
- exemptions
- discounts
Brownfield land discount
Brownfield land discount eligibility
To support regeneration and recognise the higher costs often associated with redeveloping previously developed land, qualifying developments receive a 50% discount on the standard Building Safety Levy rate.
Definition of previously developed land
The Government has adopted a definition based on the National Planning Policy Framework (NPPF), with specific amendments for Building Safety Levy purposes.
Regulations introduced in 2026 provide greater certainty about which sites qualify.
Qualifying for the brownfield discount
A development may qualify for the discounted rate if:
- the site meets the levy definition of previously developed land
- at least 75% of the planning permission red-line area meets the qualifying criteria
- none of the specified exclusions apply
Evidence required for the brownfield discount
You may be required to provide:
- planning history
- site plans
- a statement explaining the site's previous use
- any other documents requested by the Council
The Council may carry out spot checks and request additional evidence before applying the discounted rate.
Example levy calculation
Standard levy calculation example
The following example is for illustration only.
Scenario
A developer proposes:
- 40 new homes
- 300 m² of chargeable residential floorspace
- development within the Council's area
- no exemptions apply
Assume the applicable levy rate is £59.97 per m².
Calculation
Chargeable floorspace: 300 m²
Building Safety Levy:
300 × £59.97 = £17,991.00
Levy payable: £17,991.00
Brownfield discount calculation example
If the same development qualifies for the 50% brownfield discount:
Standard levy rate: £59.97/m²
Discounted levy rate: £29.98/m²
Building Safety Levy:
300 × £29.98 = £8,994.00
Levy payable: £8,994.00
Important information about levy calculations
- levy rates are set by the Government and vary between local authority areas
- the levy charge is based on verified floor space and supporting evidence submitted by the developer
- discounts and exemptions are not applied automatically and must be supported by appropriate evidence
- this example is for illustrative purposes only and should not be used to estimate charges for a live development proposal
Before submitting your application
Before submitting a building control application, you should:
- review the Government's Building Safety Levy guidance
- confirm the applicable levy rate for the development location
- check whether any exemptions or discounts may apply
- gather supporting evidence
Early engagement with the Building Control Team can help avoid delays in determining levy liability.