A developer must notify Waltham Forest Highways if any damage occurs to the highway during construction.
In the event that a dangerous defect is created on the live highway, Waltham Forest Highways must be contacted immediately. A Waltham Forest Highways engineer will then attend the site to discuss with the developer any required make safe and reinstatement works. Make safe works will be carried out immediately and recharged to the Developer, along with the costs of the permanent reinstatement works.
Whether damage is reported directly by the Developer, or if it is reported from a Highway Inspector or member of the pubic, and Highways reasonable believe the damage is due to construction activities, Highways will use S133 of the Highways Act 1980, to recharge the developer for any works necessary to repair the damage.