Highways advice service for developers

Our highways advice service gives developers expert highways advice before submitting planning conditions or highways works applications.

Highways offer an advice service for highway related planning conditions. This is offered as a pre application service, to obtain highways comments before a developer submits planning condition material to Planning for the formal discharge of planning conditions. Formalising this process enables Highways to manage the volume of requests for advice from developers. 

The Highways Advice Service is separate to the planning process and is offered so that developers can address any comments that Highways may have on key matters before submitting an application to discharge a planning condition to Planning. The Highways Advice Service cannot be used if there is a live planning condition application on the same topic.

The Highways Advice Services covers specialist planning condition topics that typically require comments and approval from a relevant technical expert, covering the matters below. The Highways Advice Service is offered for these areas:

  • Drainage
  • Construction Logistics Plans
  • Street Lighting
  • Approval in Principle (for Structures)
  • Car Park Management Plan
  • Delivery and Servicing Plan
  • Boundary Treatment
  • Wayfinding
  • Highway Condition Survey
  • Road Safety Audit

Obtaining Highway approval for these planning conditions can sometimes require multiple rounds of comments and revisions before the technical expert agrees the detail.

If a developer applies the advice or comments given via this service and receives agreement from Highways to the material submitted, the length of time for the formal planning condition process may be reduced, by minimising the number of queries raised in the formal planning consultation and number of revisions that could be requested. A letter of comfort can be issued by Highways where agreement has been given, that can then accompany a planning condition application to Planning in this instance. 

The cost of a single review, or a single meeting, for one of these planning condition matters on the topic and the size of the development. 

The cost for one hour meeting, or a single review on one of the topics below, for any size development is £180 inc VAT:

  • street lighting
  • car park management plans
  • road safety audit
  • delivery and servicing plan
  • wayfinding design
  • boundary treatment
  • highway condition survey

Cost for one meeting or single review of a Detailed CLP

The cost for a one hour meeting, or a single review of a Detailed Construction Logistics Plan (CLP) depends on the size of the development. 

Charges for a meeting or a review of a Detailed CLP
 UnitsInc VAT
Small 1-3 units£150
Medium4-9 units£240
Small scale major10-24 units, or 1000 – 4,999 sqm£360
Medium scale major25-49 units, or 5,000 – 9,999 sqm£480
Large major50-100 units, or 10,000 – 14,999 sqm£600
Strategic major 100 + units, or >15,000 sqm£720
GLA Strategic 150+ or infrastructure projects150+ units, 15,000 sqm, 30m+ high
150-299 units£900
300 – 599 units£1,140
600 - 1199£1,500
1200 – 2,999£1,680
3000 +£1,800

Cost for one meeting or single review of drainage and SuDS information

The cost for a one hour meeting, or a single review or drainage or SuDS designs depends on the size of the development and flood zone. 

Charges for a meeting or a review of SuDS and Drainage including VAT
  

One review with written comments -

flood zone 1

One review with written comments -

flood zone 2

One review with written comments -

flood zone 3

Small 

1-3 units (including flat conversions)

New build or extensions of 100sqm-499sqm

£150£180£210
Medium 

4-9 units (including flat conversions)

New build or extensions of 500sqm-999sqm

£150£180£240
Small scale major10-24 units, or 1000 – 4,999 sqm£210£240£300
Medium scale major25-49 units, or 5,000 – 9,999 sqm£240£360£480
Large major50-100 units, or 10,000 – 14,999 sqm£360£480£600
Strategic major 100 + units, or >15,000 sqm£420£540£660
GLA Strategic 150+150+ units, 15,000 sqm, 30m+ high
150-299 units£480£600£720
300 – 599 units£600£720£900
600 - 1199£900£1200£1380
1200+£120015001800
3000 +£144016801920

Admin cost for Approval in Principle (AiP)

Admin cost for the review of an AiP
ActivityStructure categoryAdmin fee
11£150
2£150
3£150
20£100
1£100
2£100
3£100
30£75
1£75
2£75
3£75

Contact the Highways Advice Service for Planning Condition topics

If you would like to make an enquiry about the Highways Advice Service, please send an email to highways.admin@walthamforest.gov.uk with the following: 

  1. The planning application number and address for the approved scheme
  2. A copy of the decision notice
  3. The number of residential units or area of commercial floorspace
  4. Which of the subject areas above you would like to be reviewed
  5. If you would like a single review of material, or request one meeting

Highways will provide a letter by email, confirming the cost of the service or services requested. If you choose to proceed you will need to:

  1. Sign and return a copy of the letter
  2. Make payment via an online link
  3. Provide a screen shot to confirm payment

When these details have been received a review or meeting will be arranged within 21 days.  Written comments will be provided from a document review, or a bullet point summary will be provided following a meeting. 

Once you have received advice from this service, you are welcome to request further rounds of meetings or documents reviews by emailing and repeating the steps above. 

Highways Advice for Development related Highways Works

The Highways Advice Service is also available to obtain advice about Development related Highways Works, before you submit an application to Highways. Charges for a one-hour meeting are shown below, Highways will price for a one or two hour meeting depending on the scope and complexity of work, the location, and the extent of information shared ahead of the meeting.

Charges for a one hour advice meeting ahead of a Developer Highway works submission  

(enabling/ temporary/ S278/ S38 works)

 UnitsInc VAT
Small 1-3 units£150
Medium4-9 units£240
Small scale major10-24 units, or 1000 – 4,999 sqm£360
Medium scale major25-49 units, or 5,000 – 9,999 sqm£480
Large major50-100 units, or 10,000 – 14,999 sqm£600
Strategic major 100 + units, or >15,000 sqm
GLA Strategic 150+ or infrastructure projects 

150+ units, 15,000 sqm, 30m+ high

150-299 units

300 – 599 units

600 - 1199

1200 – 2,999

3000 +

£900

Contact the Highways Advice Service for Development related Highways Works

If you would like to make an enquiry about the Highways Advice Service for advice about a Developer Highway Works application, ahead of submitting your application to Highways, please make your request via the link below with the following: 

  1. The planning application number and address for the approved scheme
  2. A copy of the decision notice
  3. The number of residential units or area of commercial floorspace

Highways will provide a letter by email, confirming the cost of the service requested. If you choose to proceed you will need to:

  1. Sign and return a copy of the letter
  2. Make payment via an online link
  3. Provide a screen shot to confirm payment
  4. Provide a copy of the approved ground floor plan
  5. Provide a copy of the S106 agreement (if available)
  6. Provide the boundary treatment details (approved or draft if available)
  7. Provide a copy of the waste strategy (approved or draft if available)
  8. Provide an initial plan of proposed developer highways works (enabling, temporary, S,278 or S38 works, if available)

Once payment is made and this information received, we aim to schedule a meeting within 20 working days, but this may vary.  The timescale may differ based on officer workloads and team absences.

Once you have received advice from this service, you are welcome to request further rounds of meetings or documents reviews by emailing highways.admin@walthamforest.gov.uk and repeating the steps above before making the application. 

 More information about Development Highways Works and the timeframes for applications.