Last updated: 7 November 2023

Next review: 7 November 2024

St Nicholas Court

Pre-commencement works

  • Fire Engineers and London Fire Brigade carry out independent reviews of building and fire safety design proposals. ​
  • Design works are estimated to be complete in August 2023
  • Building Control reviews and approves the design.
  • Estimated to start in late September 2023
  • Submitted Planning Application for approval in July 2023
  • Carry out consultation process for major works with leaseholders in August/September 2023

Construction works

  • Erect scaffold
  • Carry out fire risk assessment works in compliance with building safety regulations.
  • Replace windows with modern compliant materials.
  • Carry out mechanical and electrical-related work. For example, the installation of fire alarms, sprinklers, and associated infrastructure. (subject to Fire Engineer’s report) 
  • Carry out external repair works
  • Cladding renewal
  • Remove scaffolding
  • Estimated to start in late September 2023 and finish in May 2025.