St Patricks Court

Pre-commencement works​

  • Fire Engineers and London Fire Brigade carry out independent reviews of building and fire safety design proposals
    Estimated to start January 2021​ ​and finish April 2021​
  • Building Control reviews and approves design
    Estimated to start April 2021 ​​and finish August 2021​
  • Carry out consultation process for major works with leaseholders
    Started March 2022​ ​and finished April 2022​

Construction works 

  • Install new fire rated cavity barriers around penetrations through the external walls
    Estimated to start end of January 2023 and finish February 2023
  • Replace balcony soffits with modern compliant material
    Estimated to start January 2023 and finish May 2023
  • Undertake fire upgrade works to wall between external riser shafts and flats
    Estimated to start January 2023 and finish May 2023
  • Carry out communal walkway and window works
    Estimated to start November 2022 and finish April 2023
  • Remove and renew cavity wall insulation
    Estimated start end of January 2023 and finish May 2023
  • Remove scaffolding
    Estimated start May 2023 and finish June 2023
  • Carry out mechanical and electrical related works e.g. installation of fire alarms (subject to Fire Engineer’s report)
    Estimated to start April 2023 and finish September 2023