St Davids Court

Pre-commencement works​

Design phase I  

  • Identification pre-design of works
    Estimated – June 2021 – July 2021

Design phase II  

  • Fire Engineers and London Fire Brigade carry out independent reviews of building and fire safety design proposals.
    Estimated to start November 2021 ​and finish June 2022
  • Building Control reviews and approves design
    Estimated to start November 2021 ​and finish June 2022
  • Carry out consultation process for major works with leaseholders. ​
    Estimated to start September 2022 ​and finish October 2022
  • Structural investigations
    August 2021 – October 2021

Construction Works 

  • Erect scaffold​
    Estimated to start October 2022 ​and finish December 2022
  • Carry out works to external coating that are compliant with building safety regulations​
    Estimated to start December 2022 ​and finish March 2023
  • Replace balcony soffits with modern compliant materials ​
    Estimated to start January 2023 ​and finish March 2023
  • Install Automatic Opening Vents to the head of the stairwell
    Estimated to start January 2023 ​and finish February 2023
  • Undertake fire upgrade works to the wall between external riser shafts and flats​
    Estimated to start February 2023 ​and finish March 2023
  • Replace windows between flats and internal communal hallways with new fire rated windows
    Estimation to be confirmed 
  • Remove scaffold
    Estimation to start April 2023 ​and finish May 2023