Click here to activate screen reader, translation and accessibility tools

Northwood Tower

Pre-commencement works​

  • Fire Engineers and London Fire Brigade carry out independent reviews of building and fire safety design proposals.
    Estimated to start January 2021​ ​and finish February 2021​
  • Carry out consultation process for major works with leaseholders
    Estimated to start March 2021​ ​and finish May 2021​
  • Building Control reviews and approves design
    Estimated to start March 2021​ ​and finish July 2021​

Construction Works 

  • Erect scaffold
    Estimated to start September 2021​ ​and finish November 2021​
  • Replace balcony soffits with modern compliant materials
    Estimated to start December 2021​ ​and finish February 2022​
  • Install new Infill panels to external windows to bin chute
    Estimated to start December 2021​ ​and finish January 2022​
  • Remove scaffolding
    Estimated to start February 2022​ ​and finish March 2022​